Rose Valley Substation


Rose Valley

With new services needed in northern Oklahoma, CEC was tasked with the design and layout for the Rose Valley Substation in Woods County, OK. From the raw land development, CEC Power Delivery was able to team with the Facilities Division to design this 138kV/34.5kV step down substation project for Western Farmers Electric Cooperative (WFEC) and Alfalfa Electric Cooperative.

The design of the step down substation included survey, site layout and draining, electrical grid design, SP&C Substation Design, transmission line design, foundation design, as well as construction drawings for the standard WFEC substation BUS and two transmission flat switches.  All services were able to be performed in-house by CEC team members.