Chickasha Toll Plaza


Chickasha Toll Plaza

The scope of this project was to relocate the Chickasha Toll Plaza on the H.E. Bailey Turnpike which included grading, drainage, paving, lighting, striping, signing, a new toll plaza at milepost 66.62 and demolition of existing toll plaza at milepost 77.98. This project is located in Caddo and Grady Counties and is part of the Oklahoma Turnpike Authority “Driving Forward” program.

CEC provided level 1: On-Site Representative (OSR) services. These duties included: oversight of construction contract, daily reports, quantities, producing pay estimates, documentation and oversight as the direct contact for the Contractor. We were also responsible for submitting all documentation, RFI’s, pay estimates, and other reports to the Construction Manager.